{"slug":"construction-project-gantt-schedule","sheets":[{"name":"لوحة التحكم ومؤشرات الجدول","maxRow":16,"maxCol":9,"colWidths":[8.0,58.0,16.0,16.0,16.0,16.0,18.0,18.0,44.0],"rows":[{"r":1,"h":54.0,"cells":[{"c":"A1","v":"لوحة التحكم التنفيذية للبرنامج الزمني ومؤشرات الأداء (Gantt & SPI Dashboard)","bg":"#0F172A","fg":"#FFFFFF","b":true,"al":"center","cs":9},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":2,"h":56.0,"cells":[{"c":"A2","v":"متابعة المسار الحرج، نسب الإنجاز المخططة مقابل الفعلية، ومعامل الأداء الزمني SPI وفق منهجية PMBOK وعقود الفيديك","bg":"#1D4ED8","fg":"#DBEAFE","al":"center","cs":9},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":3,"h":12.0,"cells":[{"c":"A3","v":""},{"c":"B3","v":""},{"c":"C3","v":""},{"c":"D3","v":""},{"c":"E3","v":""},{"c":"F3","v":""},{"c":"G3","v":""},{"c":"H3","v":""},{"c":"I3","v":""}]},{"r":4,"h":34.0,"cells":[{"c":"A4","v":"إجمالي أنشطة البرنامج (WBS)","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center","cs":2},{"skip":true},{"c":"C4","v":"نسبة الإنجاز المخططة التراكمية","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center","cs":2},{"skip":true},{"c":"E4","v":"نسبة الإنجاز الفعلي التراكمية","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center","cs":3},{"skip":true},{"skip":true},{"c":"H4","v":"معامل الأداء الزمني (SPI)","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center","cs":2},{"skip":true}]},{"r":5,"h":42.0,"cells":[{"c":"A5","v":14,"f":"=COUNTA('البرنامج الزمني ومخطط جانت'!B6:B19)","bg":"#E2E8F0","b":true,"al":"center","nf":"#,##0","cs":2},{"skip":true},{"c":"C5","v":0.587,"f":"=SUMPRODUCT('البرنامج الزمني ومخطط جانت'!G6:G19,'البرنامج الزمني ومخطط جانت'!H6:H19)","bg":"#EFF6FF","b":true,"al":"center","nf":"0.0%","cs":2},{"skip":true},{"c":"E5","v":0.5656,"f":"=SUMPRODUCT('البرنامج الزمني ومخطط جانت'!G6:G19,'البرنامج الزمني ومخطط جانت'!I6:I19)","bg":"#DCFCE7","b":true,"al":"center","nf":"0.0%","cs":3},{"skip":true},{"skip":true},{"c":"H5","v":0.963543,"f":"=E5/C5","bg":"#FEF3C7","b":true,"al":"center","nf":"0.00","cs":2},{"skip":true}]},{"r":6,"h":34.0,"cells":[{"c":"A6","v":"نشاطاً رئيسياً بالمشروع","bg":"#F1F5F9","fg":"#64748B","al":"center","cs":2},{"skip":true},{"c":"C6","v":"Planned Progress %","bg":"#F1F5F9","fg":"#64748B","al":"center","cs":2},{"skip":true},{"c":"E6","v":"Actual Progress %","bg":"#F1F5F9","fg":"#64748B","al":"center","cs":3},{"skip":true},{"skip":true},{"c":"H6","v":"SPI = EV / PV (مؤشر تقدم الجدول)","bg":"#F1F5F9","fg":"#64748B","al":"center","cs":2},{"skip":true}]},{"r":7,"h":14.0,"cells":[{"c":"A7","v":""},{"c":"B7","v":""},{"c":"C7","v":""},{"c":"D7","v":""},{"c":"E7","v":""},{"c":"F7","v":""},{"c":"G7","v":""},{"c":"H7","v":""},{"c":"I7","v":""}]},{"r":8,"h":38.0,"cells":[{"c":"A8","v":"ملخص الأوزان النسبية ونسب الإنجاز حسب المراحل الهندسية الرئيسية (WBS Summary)","bg":"#1E293B","fg":"#FFFFFF","b":true,"cs":9},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":9,"h":40.0,"cells":[{"c":"A9","v":"م","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B9","v":"مرحلة العمل الرئيسية (WBS Phase)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C9","v":"المدة (يوم)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D9","v":"الوزن النسبي %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E9","v":"المخطط %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"F9","v":"الفعلي %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"G9","v":"الانحراف الزمني %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"H9","v":"حالة المسار الحرج","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"I9","v":"التقييم الفني للمرحلة","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":10,"h":34.0,"cells":[{"c":"A10","v":1,"b":true,"al":"center"},{"c":"B10","v":"التجهيزات الموقعـية والأعمال التمهيدية والحفر","b":true},{"c":"C10","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"D10","v":0.12,"f":"=SUM('البرنامج الزمني ومخطط جانت'!G6:G8)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"E10","v":1,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!H6:H8)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"F10","v":1,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!I6:I8)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"G10","v":0,"f":"=F10-E10","b":true,"al":"center","nf":"0.0%"},{"c":"H10","v":"مسار حرج","fg":"#1E293B","al":"center"},{"c":"I10","v":"مكتمل بالكامل وفق الجدول المرجعي","fg":"#1E293B"}]},{"r":11,"h":34.0,"cells":[{"c":"A11","v":2,"b":true,"al":"center"},{"c":"B11","v":"أعمال الأساسات والهيكل الخرساني المسلح","b":true},{"c":"C11","v":150,"in":true,"fg":"#1E293B","al":"center"},{"c":"D11","v":0.41,"f":"=SUM('البرنامج الزمني ومخطط جانت'!G9:G12)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"E11","v":0.8875,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!H9:H12)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"F11","v":0.8575,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!I9:I12)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"G11","v":-0.03,"f":"=F11-E11","b":true,"al":"center","nf":"0.0%"},{"c":"H11","v":"مسار حرج","fg":"#1E293B","al":"center"},{"c":"I11","v":"تقدم منتظم في صب الأسقف المتكررة","fg":"#1E293B"}]},{"r":12,"h":34.0,"cells":[{"c":"A12","v":3,"b":true,"al":"center"},{"c":"B12","v":"أعمال المباني والتشطيبات المعمارية والواجهات","b":true},{"c":"C12","v":135,"in":true,"fg":"#1E293B","al":"center"},{"c":"D12","v":0.28,"f":"=SUM('البرنامج الزمني ومخطط جانت'!G13:G16)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"E12","v":0.35,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!H13:H16)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"F12","v":0.325,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!I13:I16)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"G12","v":-0.025,"f":"=F12-E12","b":true,"al":"center","nf":"0.0%"},{"c":"H12","v":"شبه حرج","fg":"#1E293B","al":"center"},{"c":"I12","v":"جارٍ تنفيذ المحارة وتوريد البورسلين","fg":"#1E293B"}]},{"r":13,"h":34.0,"cells":[{"c":"A13","v":4,"b":true,"al":"center"},{"c":"B13","v":"الأعمال الكهروميكانيكية والاختبارات والتسليم","b":true},{"c":"C13","v":120,"in":true,"fg":"#1E293B","al":"center"},{"c":"D13","v":0.19,"f":"=SUM('البرنامج الزمني ومخطط جانت'!G17:G19)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"E13","v":0,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!H17:H19)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"F13","v":0,"f":"=AVERAGE('البرنامج الزمني ومخطط جانت'!I17:I19)","fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"G13","v":0,"f":"=F13-E13","b":true,"al":"center","nf":"0.0%"},{"c":"H13","v":"مسار حرج","fg":"#1E293B","al":"center"},{"c":"I13","v":"تمديدات التأسيس جارية وفق المخطط","fg":"#1E293B"}]},{"r":14,"h":40.0,"cells":[{"c":"A14","v":"الإجمالي الكلي للمشروع (Total Project Baseline)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","cs":2},{"skip":true},{"c":"C14","v":360,"f":"=MAX(C10:C13)*2.4","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","nf":"#,##0"},{"c":"D14","v":1,"f":"=SUM(D10:D13)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","nf":"0.0%"},{"c":"E14","v":0.587,"f":"=C5","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","nf":"0.0%"},{"c":"F14","v":0.5656,"f":"=E5","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","nf":"0.0%"},{"c":"G14","v":-0.0214,"f":"=F14-E14","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","nf":"0.0%"},{"c":"H14","v":"12 شهراً","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"I14","v":"يوجد تأخر يستوجب خطة تعويض","f":"=IF(G14>=0, \"المشروع متقدم / مطابق للجدول\", \"يوجد تأخر يستوجب خطة تعويض\")","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":15,"h":14.0,"cells":[{"c":"A15","v":""},{"c":"B15","v":""},{"c":"C15","v":""},{"c":"D15","v":""},{"c":"E15","v":""},{"c":"F15","v":""},{"c":"G15","v":""},{"c":"H15","v":""},{"c":"I15","v":""}]},{"r":16,"h":75.0,"cells":[{"c":"A16","v":"إعداد مهندس التخطيط والمكتب الفني\nالاسم: .........................................\nالتوقيع والتاريخ: .............................","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true},{"c":"D16","v":"مراجعة وتدقيق مدير المشروع\nالاسم: .........................................\nالتوقيع والتاريخ: .............................","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true},{"c":"G16","v":"اعتماد المهندس الاستشاري المشرف\nالاسم: .........................................\nالتوقيع والختم: ...............................","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true}]}]},{"name":"البرنامج الزمني ومخطط جانت","maxRow":19,"maxCol":22,"colWidths":[12.0,58.0,12.0,12.0,12.0,12.0,12.0,12.0,12.0,14.0,7.5,7.5,7.5,7.5,7.5,7.5,7.5,7.5,7.5,7.5,7.5,7.5],"rows":[{"r":1,"h":54.0,"cells":[{"c":"A1","v":"البرنامج الزمني التفصيلي للأنشطة ومخطط جانت الشهري (12-Month Construction Gantt Schedule)","bg":"#0F172A","fg":"#FFFFFF","b":true,"al":"center","cs":22},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":2,"h":56.0,"cells":[{"c":"A2","v":"يتم تلوين شريط جانت تلقائياً بناءً على شهر البدء وشهر الانتهاء لكل نشاط مع حساب الانحرافات الزمنية والمسار الحرج","bg":"#1D4ED8","fg":"#DBEAFE","al":"center","cs":22},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":3,"h":12.0,"cells":[{"c":"A3","v":""},{"c":"B3","v":""},{"c":"C3","v":""},{"c":"D3","v":""},{"c":"E3","v":""},{"c":"F3","v":""},{"c":"G3","v":""},{"c":"H3","v":""},{"c":"I3","v":""},{"c":"J3","v":""},{"c":"K3","v":""},{"c":"L3","v":""},{"c":"M3","v":""},{"c":"N3","v":""},{"c":"O3","v":""},{"c":"P3","v":""},{"c":"Q3","v":""},{"c":"R3","v":""},{"c":"S3","v":""},{"c":"T3","v":""},{"c":"U3","v":""},{"c":"V3","v":""}]},{"r":4,"h":38.0,"cells":[{"c":"A4","v":"بيانات أنشطة هيكل تجزئة العمل (WBS Activities & Weights)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","cs":10},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"c":"K4","v":"مخطط جانت الزمني للأشهر (M1 إلى M12 - Visual Gantt Timeline)","bg":"#1D4ED8","fg":"#FFFFFF","b":true,"al":"center","cs":12},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":5,"h":40.0,"cells":[{"c":"A5","v":"كود WBS","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B5","v":"بيان النشاط الهندسي (Activity Description)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C5","v":"الاعتمادية","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D5","v":"المدة (يوم)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E5","v":"شهر البدء","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"F5","v":"شهر النهاية","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"G5","v":"الوزن %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"H5","v":"المخطط %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"I5","v":"الفعلي %","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"J5","v":"المسار","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"K5","v":"M1","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"L5","v":"M2","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"M5","v":"M3","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"N5","v":"M4","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"O5","v":"M5","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"P5","v":"M6","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"Q5","v":"M7","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"R5","v":"M8","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"S5","v":"M9","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"T5","v":"M10","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"U5","v":"M11","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"},{"c":"V5","v":"M12","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":6,"h":34.0,"cells":[{"c":"A6","v":"WBS-01","b":true,"al":"center"},{"c":"B6","v":"استلام الموقع، الرفع المساحي، وتجهيز المكاتب والسور المؤقت","b":true},{"c":"C6","v":"-","fg":"#1E293B","al":"center"},{"c":"D6","v":20,"in":true,"fg":"#1E293B","al":"center"},{"c":"E6","v":1,"in":true,"fg":"#1E293B","al":"center"},{"c":"F6","v":1,"in":true,"fg":"#1E293B","al":"center"},{"c":"G6","v":0.03,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H6","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I6","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J6","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K6","v":"","f":"=IF(AND(1>=$E6,1<=$F6),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"L6","v":"","f":"=IF(AND(2>=$E6,2<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M6","v":"","f":"=IF(AND(3>=$E6,3<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N6","v":"","f":"=IF(AND(4>=$E6,4<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O6","v":"","f":"=IF(AND(5>=$E6,5<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P6","v":"","f":"=IF(AND(6>=$E6,6<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q6","v":"","f":"=IF(AND(7>=$E6,7<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R6","v":"","f":"=IF(AND(8>=$E6,8<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S6","v":"","f":"=IF(AND(9>=$E6,9<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T6","v":"","f":"=IF(AND(10>=$E6,10<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U6","v":"","f":"=IF(AND(11>=$E6,11<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V6","v":"","f":"=IF(AND(12>=$E6,12<=$F6),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":7,"h":34.0,"cells":[{"c":"A7","v":"WBS-02","b":true,"al":"center"},{"c":"B7","v":"أعمال الحفر الميكانيكي العام حتى منسوب التأسيس وسند الجوانب","b":true},{"c":"C7","v":"WBS-01","fg":"#1E293B","al":"center"},{"c":"D7","v":25,"in":true,"fg":"#1E293B","al":"center"},{"c":"E7","v":1,"in":true,"fg":"#1E293B","al":"center"},{"c":"F7","v":2,"in":true,"fg":"#1E293B","al":"center"},{"c":"G7","v":0.05,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H7","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I7","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J7","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K7","v":"","f":"=IF(AND(1>=$E7,1<=$F7),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"L7","v":"","f":"=IF(AND(2>=$E7,2<=$F7),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"M7","v":"","f":"=IF(AND(3>=$E7,3<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N7","v":"","f":"=IF(AND(4>=$E7,4<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O7","v":"","f":"=IF(AND(5>=$E7,5<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P7","v":"","f":"=IF(AND(6>=$E7,6<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q7","v":"","f":"=IF(AND(7>=$E7,7<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R7","v":"","f":"=IF(AND(8>=$E7,8<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S7","v":"","f":"=IF(AND(9>=$E7,9<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T7","v":"","f":"=IF(AND(10>=$E7,10<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U7","v":"","f":"=IF(AND(11>=$E7,11<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V7","v":"","f":"=IF(AND(12>=$E7,12<=$F7),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":8,"h":34.0,"cells":[{"c":"A8","v":"WBS-03","b":true,"al":"center"},{"c":"B8","v":"الردم بالإحلال المدموك، خرسانة النظافة، وعزل الأساسات","b":true},{"c":"C8","v":"WBS-02","fg":"#1E293B","al":"center"},{"c":"D8","v":20,"in":true,"fg":"#1E293B","al":"center"},{"c":"E8","v":2,"in":true,"fg":"#1E293B","al":"center"},{"c":"F8","v":2,"in":true,"fg":"#1E293B","al":"center"},{"c":"G8","v":0.04,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H8","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I8","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J8","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K8","v":"","f":"=IF(AND(1>=$E8,1<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L8","v":"","f":"=IF(AND(2>=$E8,2<=$F8),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"M8","v":"","f":"=IF(AND(3>=$E8,3<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N8","v":"","f":"=IF(AND(4>=$E8,4<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O8","v":"","f":"=IF(AND(5>=$E8,5<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P8","v":"","f":"=IF(AND(6>=$E8,6<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q8","v":"","f":"=IF(AND(7>=$E8,7<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R8","v":"","f":"=IF(AND(8>=$E8,8<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S8","v":"","f":"=IF(AND(9>=$E8,9<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T8","v":"","f":"=IF(AND(10>=$E8,10<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U8","v":"","f":"=IF(AND(11>=$E8,11<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V8","v":"","f":"=IF(AND(12>=$E8,12<=$F8),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":9,"h":34.0,"cells":[{"c":"A9","v":"WBS-04","b":true,"al":"center"},{"c":"B9","v":"نجارة وحدادة وصب القواعد المسلحة والشدادات والسملات ورقاب الأعمدة","b":true},{"c":"C9","v":"WBS-03","fg":"#1E293B","al":"center"},{"c":"D9","v":35,"in":true,"fg":"#1E293B","al":"center"},{"c":"E9","v":2,"in":true,"fg":"#1E293B","al":"center"},{"c":"F9","v":3,"in":true,"fg":"#1E293B","al":"center"},{"c":"G9","v":0.1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H9","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I9","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J9","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K9","v":"","f":"=IF(AND(1>=$E9,1<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L9","v":"","f":"=IF(AND(2>=$E9,2<=$F9),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"M9","v":"","f":"=IF(AND(3>=$E9,3<=$F9),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"N9","v":"","f":"=IF(AND(4>=$E9,4<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O9","v":"","f":"=IF(AND(5>=$E9,5<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P9","v":"","f":"=IF(AND(6>=$E9,6<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q9","v":"","f":"=IF(AND(7>=$E9,7<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R9","v":"","f":"=IF(AND(8>=$E9,8<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S9","v":"","f":"=IF(AND(9>=$E9,9<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T9","v":"","f":"=IF(AND(10>=$E9,10<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U9","v":"","f":"=IF(AND(11>=$E9,11<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V9","v":"","f":"=IF(AND(12>=$E9,12<=$F9),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":10,"h":34.0,"cells":[{"c":"A10","v":"WBS-05","b":true,"al":"center"},{"c":"B10","v":"صب أعمدة وبلاطة سقف الدور الأرضي والأول المتكرر","b":true},{"c":"C10","v":"WBS-04","fg":"#1E293B","al":"center"},{"c":"D10","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"E10","v":3,"in":true,"fg":"#1E293B","al":"center"},{"c":"F10","v":5,"in":true,"fg":"#1E293B","al":"center"},{"c":"G10","v":0.12,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H10","v":1,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I10","v":0.95,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J10","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K10","v":"","f":"=IF(AND(1>=$E10,1<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L10","v":"","f":"=IF(AND(2>=$E10,2<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M10","v":"","f":"=IF(AND(3>=$E10,3<=$F10),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"N10","v":"","f":"=IF(AND(4>=$E10,4<=$F10),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"O10","v":"","f":"=IF(AND(5>=$E10,5<=$F10),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"P10","v":"","f":"=IF(AND(6>=$E10,6<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q10","v":"","f":"=IF(AND(7>=$E10,7<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R10","v":"","f":"=IF(AND(8>=$E10,8<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S10","v":"","f":"=IF(AND(9>=$E10,9<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T10","v":"","f":"=IF(AND(10>=$E10,10<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U10","v":"","f":"=IF(AND(11>=$E10,11<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V10","v":"","f":"=IF(AND(12>=$E10,12<=$F10),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":11,"h":34.0,"cells":[{"c":"A11","v":"WBS-06","b":true,"al":"center"},{"c":"B11","v":"صب أعمدة وبلاطات الأدوار المتكررة العليا وسقف السطح النهائي","b":true},{"c":"C11","v":"WBS-05","fg":"#1E293B","al":"center"},{"c":"D11","v":50,"in":true,"fg":"#1E293B","al":"center"},{"c":"E11","v":5,"in":true,"fg":"#1E293B","al":"center"},{"c":"F11","v":6,"in":true,"fg":"#1E293B","al":"center"},{"c":"G11","v":0.12,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H11","v":0.85,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I11","v":0.8,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J11","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K11","v":"","f":"=IF(AND(1>=$E11,1<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L11","v":"","f":"=IF(AND(2>=$E11,2<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M11","v":"","f":"=IF(AND(3>=$E11,3<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N11","v":"","f":"=IF(AND(4>=$E11,4<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O11","v":"","f":"=IF(AND(5>=$E11,5<=$F11),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"P11","v":"","f":"=IF(AND(6>=$E11,6<=$F11),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q11","v":"","f":"=IF(AND(7>=$E11,7<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R11","v":"","f":"=IF(AND(8>=$E11,8<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S11","v":"","f":"=IF(AND(9>=$E11,9<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T11","v":"","f":"=IF(AND(10>=$E11,10<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U11","v":"","f":"=IF(AND(11>=$E11,11<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V11","v":"","f":"=IF(AND(12>=$E11,12<=$F11),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":12,"h":34.0,"cells":[{"c":"A12","v":"WBS-07","b":true,"al":"center"},{"c":"B12","v":"أعمال المباني الطوبية للقواطيع الداخلية والحوائط الخارجية","b":true},{"c":"C12","v":"WBS-05","fg":"#1E293B","al":"center"},{"c":"D12","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"E12","v":5,"in":true,"fg":"#1E293B","al":"center"},{"c":"F12","v":7,"in":true,"fg":"#1E293B","al":"center"},{"c":"G12","v":0.07,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H12","v":0.7,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I12","v":0.68,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J12","v":"غير حرج","b":true,"al":"center"},{"c":"K12","v":"","f":"=IF(AND(1>=$E12,1<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"L12","v":"","f":"=IF(AND(2>=$E12,2<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"M12","v":"","f":"=IF(AND(3>=$E12,3<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"N12","v":"","f":"=IF(AND(4>=$E12,4<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"O12","v":"","f":"=IF(AND(5>=$E12,5<=$F12),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"P12","v":"","f":"=IF(AND(6>=$E12,6<=$F12),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"Q12","v":"","f":"=IF(AND(7>=$E12,7<=$F12),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"R12","v":"","f":"=IF(AND(8>=$E12,8<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"S12","v":"","f":"=IF(AND(9>=$E12,9<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"T12","v":"","f":"=IF(AND(10>=$E12,10<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"U12","v":"","f":"=IF(AND(11>=$E12,11<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"V12","v":"","f":"=IF(AND(12>=$E12,12<=$F12),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"}]},{"r":13,"h":52.0,"cells":[{"c":"A13","v":"WBS-08","b":true,"al":"center"},{"c":"B13","v":"التأسيسات الكهروميكانيكية الأولية (خراطيم الكهرباء ومواسير التغذية والصرف)","b":true},{"c":"C13","v":"WBS-07","fg":"#1E293B","al":"center"},{"c":"D13","v":50,"in":true,"fg":"#1E293B","al":"center"},{"c":"E13","v":6,"in":true,"fg":"#1E293B","al":"center"},{"c":"F13","v":8,"in":true,"fg":"#1E293B","al":"center"},{"c":"G13","v":0.08,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H13","v":0.5,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I13","v":0.48,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J13","v":"غير حرج","b":true,"al":"center"},{"c":"K13","v":"","f":"=IF(AND(1>=$E13,1<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"L13","v":"","f":"=IF(AND(2>=$E13,2<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"M13","v":"","f":"=IF(AND(3>=$E13,3<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"N13","v":"","f":"=IF(AND(4>=$E13,4<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"O13","v":"","f":"=IF(AND(5>=$E13,5<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"P13","v":"","f":"=IF(AND(6>=$E13,6<=$F13),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"Q13","v":"","f":"=IF(AND(7>=$E13,7<=$F13),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"R13","v":"","f":"=IF(AND(8>=$E13,8<=$F13),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"S13","v":"","f":"=IF(AND(9>=$E13,9<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"T13","v":"","f":"=IF(AND(10>=$E13,10<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"U13","v":"","f":"=IF(AND(11>=$E13,11<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"V13","v":"","f":"=IF(AND(12>=$E13,12<=$F13),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"}]},{"r":14,"h":34.0,"cells":[{"c":"A14","v":"WBS-09","b":true,"al":"center"},{"c":"B14","v":"أعمال الطرطشة والبؤج واللياسة (بياض المحارة الداخلي والخارجي)","b":true},{"c":"C14","v":"WBS-08","fg":"#1E293B","al":"center"},{"c":"D14","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"E14","v":7,"in":true,"fg":"#1E293B","al":"center"},{"c":"F14","v":9,"in":true,"fg":"#1E293B","al":"center"},{"c":"G14","v":0.08,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H14","v":0.35,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I14","v":0.3,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J14","v":"شبه حرج","b":true,"al":"center"},{"c":"K14","v":"","f":"=IF(AND(1>=$E14,1<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"L14","v":"","f":"=IF(AND(2>=$E14,2<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"M14","v":"","f":"=IF(AND(3>=$E14,3<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"N14","v":"","f":"=IF(AND(4>=$E14,4<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"O14","v":"","f":"=IF(AND(5>=$E14,5<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"P14","v":"","f":"=IF(AND(6>=$E14,6<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"Q14","v":"","f":"=IF(AND(7>=$E14,7<=$F14),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"R14","v":"","f":"=IF(AND(8>=$E14,8<=$F14),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"S14","v":"","f":"=IF(AND(9>=$E14,9<=$F14),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"T14","v":"","f":"=IF(AND(10>=$E14,10<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"U14","v":"","f":"=IF(AND(11>=$E14,11<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"V14","v":"","f":"=IF(AND(12>=$E14,12<=$F14),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"}]},{"r":15,"h":34.0,"cells":[{"c":"A15","v":"WBS-10","b":true,"al":"center"},{"c":"B15","v":"أعمال العزل المائي والحراري للأسطح والحمامات واختبارات الغمر","b":true},{"c":"C15","v":"WBS-06","fg":"#1E293B","al":"center"},{"c":"D15","v":25,"in":true,"fg":"#1E293B","al":"center"},{"c":"E15","v":7,"in":true,"fg":"#1E293B","al":"center"},{"c":"F15","v":8,"in":true,"fg":"#1E293B","al":"center"},{"c":"G15","v":0.04,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H15","v":0.4,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I15","v":0.4,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J15","v":"غير حرج","b":true,"al":"center"},{"c":"K15","v":"","f":"=IF(AND(1>=$E15,1<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"L15","v":"","f":"=IF(AND(2>=$E15,2<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"M15","v":"","f":"=IF(AND(3>=$E15,3<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"N15","v":"","f":"=IF(AND(4>=$E15,4<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"O15","v":"","f":"=IF(AND(5>=$E15,5<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"P15","v":"","f":"=IF(AND(6>=$E15,6<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"Q15","v":"","f":"=IF(AND(7>=$E15,7<=$F15),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"R15","v":"","f":"=IF(AND(8>=$E15,8<=$F15),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"S15","v":"","f":"=IF(AND(9>=$E15,9<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"T15","v":"","f":"=IF(AND(10>=$E15,10<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"U15","v":"","f":"=IF(AND(11>=$E15,11<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"V15","v":"","f":"=IF(AND(12>=$E15,12<=$F15),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"}]},{"r":16,"h":34.0,"cells":[{"c":"A16","v":"WBS-11","b":true,"al":"center"},{"c":"B16","v":"أعمال تكسيات الأرضيات والحوائط (البورسلين، السيراميك، والرخام)","b":true},{"c":"C16","v":"WBS-09","fg":"#1E293B","al":"center"},{"c":"D16","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"E16","v":8,"in":true,"fg":"#1E293B","al":"center"},{"c":"F16","v":10,"in":true,"fg":"#1E293B","al":"center"},{"c":"G16","v":0.08,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H16","v":0.15,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I16","v":0.12,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J16","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K16","v":"","f":"=IF(AND(1>=$E16,1<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L16","v":"","f":"=IF(AND(2>=$E16,2<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M16","v":"","f":"=IF(AND(3>=$E16,3<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N16","v":"","f":"=IF(AND(4>=$E16,4<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O16","v":"","f":"=IF(AND(5>=$E16,5<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P16","v":"","f":"=IF(AND(6>=$E16,6<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q16","v":"","f":"=IF(AND(7>=$E16,7<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R16","v":"","f":"=IF(AND(8>=$E16,8<=$F16),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"S16","v":"","f":"=IF(AND(9>=$E16,9<=$F16),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"T16","v":"","f":"=IF(AND(10>=$E16,10<=$F16),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"U16","v":"","f":"=IF(AND(11>=$E16,11<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"V16","v":"","f":"=IF(AND(12>=$E16,12<=$F16),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":17,"h":34.0,"cells":[{"c":"A17","v":"WBS-12","b":true,"al":"center"},{"c":"B17","v":"أعمال الأسقف المستعارة (الجبس بورد) ومعجون ودهانات الحوائط","b":true},{"c":"C17","v":"WBS-11","fg":"#1E293B","al":"center"},{"c":"D17","v":45,"in":true,"fg":"#1E293B","al":"center"},{"c":"E17","v":9,"in":true,"fg":"#1E293B","al":"center"},{"c":"F17","v":11,"in":true,"fg":"#1E293B","al":"center"},{"c":"G17","v":0.06,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H17","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I17","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J17","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K17","v":"","f":"=IF(AND(1>=$E17,1<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L17","v":"","f":"=IF(AND(2>=$E17,2<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M17","v":"","f":"=IF(AND(3>=$E17,3<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N17","v":"","f":"=IF(AND(4>=$E17,4<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O17","v":"","f":"=IF(AND(5>=$E17,5<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P17","v":"","f":"=IF(AND(6>=$E17,6<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q17","v":"","f":"=IF(AND(7>=$E17,7<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R17","v":"","f":"=IF(AND(8>=$E17,8<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S17","v":"","f":"=IF(AND(9>=$E17,9<=$F17),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"T17","v":"","f":"=IF(AND(10>=$E17,10<=$F17),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"U17","v":"","f":"=IF(AND(11>=$E17,11<=$F17),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"V17","v":"","f":"=IF(AND(12>=$E17,12<=$F17),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"}]},{"r":18,"h":34.0,"cells":[{"c":"A18","v":"WBS-13","b":true,"al":"center"},{"c":"B18","v":"تركيب قطاعات الألومنيوم والزجاج، الأبواب الخشبية، والواجهات","b":true},{"c":"C18","v":"WBS-09","fg":"#1E293B","al":"center"},{"c":"D18","v":40,"in":true,"fg":"#1E293B","al":"center"},{"c":"E18","v":9,"in":true,"fg":"#1E293B","al":"center"},{"c":"F18","v":11,"in":true,"fg":"#1E293B","al":"center"},{"c":"G18","v":0.05,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H18","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I18","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J18","v":"غير حرج","b":true,"al":"center"},{"c":"K18","v":"","f":"=IF(AND(1>=$E18,1<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"L18","v":"","f":"=IF(AND(2>=$E18,2<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"M18","v":"","f":"=IF(AND(3>=$E18,3<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"N18","v":"","f":"=IF(AND(4>=$E18,4<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"O18","v":"","f":"=IF(AND(5>=$E18,5<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"P18","v":"","f":"=IF(AND(6>=$E18,6<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"Q18","v":"","f":"=IF(AND(7>=$E18,7<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"R18","v":"","f":"=IF(AND(8>=$E18,8<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"},{"c":"S18","v":"","f":"=IF(AND(9>=$E18,9<=$F18),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"T18","v":"","f":"=IF(AND(10>=$E18,10<=$F18),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"U18","v":"","f":"=IF(AND(11>=$E18,11<=$F18),\"███\",\"\")","bg":"#EFF6FF","fg":"#1D4ED8","b":true,"al":"center"},{"c":"V18","v":"","f":"=IF(AND(12>=$E18,12<=$F18),\"███\",\"\")","fg":"#1D4ED8","b":true,"al":"center"}]},{"r":19,"h":52.0,"cells":[{"c":"A19","v":"WBS-14","b":true,"al":"center"},{"c":"B19","v":"تركيب اللوحات الكهربائية، التكييف، الاختبارات والتشغيل، والتسليم الابتدائي","b":true},{"c":"C19","v":"WBS-12","fg":"#1E293B","al":"center"},{"c":"D19","v":35,"in":true,"fg":"#1E293B","al":"center"},{"c":"E19","v":11,"in":true,"fg":"#1E293B","al":"center"},{"c":"F19","v":12,"in":true,"fg":"#1E293B","al":"center"},{"c":"G19","v":0.08,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"H19","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"I19","v":0,"in":true,"fg":"#1E293B","al":"center","nf":"0.0%"},{"c":"J19","v":"حرج (CP)","bg":"#FEE2E2","b":true,"al":"center"},{"c":"K19","v":"","f":"=IF(AND(1>=$E19,1<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"L19","v":"","f":"=IF(AND(2>=$E19,2<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"M19","v":"","f":"=IF(AND(3>=$E19,3<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"N19","v":"","f":"=IF(AND(4>=$E19,4<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"O19","v":"","f":"=IF(AND(5>=$E19,5<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"P19","v":"","f":"=IF(AND(6>=$E19,6<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"Q19","v":"","f":"=IF(AND(7>=$E19,7<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"R19","v":"","f":"=IF(AND(8>=$E19,8<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"S19","v":"","f":"=IF(AND(9>=$E19,9<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"T19","v":"","f":"=IF(AND(10>=$E19,10<=$F19),\"███\",\"\")","fg":"#B91C1C","b":true,"al":"center"},{"c":"U19","v":"","f":"=IF(AND(11>=$E19,11<=$F19),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"},{"c":"V19","v":"","f":"=IF(AND(12>=$E19,12<=$F19),\"███\",\"\")","bg":"#FEF3C7","fg":"#B91C1C","b":true,"al":"center"}]}]}]}