{"slug":"punch-list-and-handover-defect-tracker","sheets":[{"name":"لوحة المؤشرات والملخص","maxRow":22,"maxCol":7,"colWidths":[22.0,24.0,24.0,24.0,24.0,24.0,22.0],"rows":[{"r":1,"h":54.0,"cells":[{"c":"A1","v":"📊 لوحة متابعة ملاحظات الاستلام الابتدائي والنهائي للمشروع (Punch List Dashboard)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","cs":7},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":2,"h":54.0,"cells":[{"c":"A2","v":"مشروع: إنشاء برج سكني وتجاري - مرحلة الاستلام الابتدائي والتسليم الهندسي وفق كود SBC 201 وشروط عقد الفيديك (FIDIC)","fg":"#64748B","al":"center","cs":7},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":3,"h":28.0,"cells":[{"c":"A3","v":""},{"c":"B3","v":""},{"c":"C3","v":""},{"c":"D3","v":""},{"c":"E3","v":""},{"c":"F3","v":""},{"c":"G3","v":""}]},{"r":4,"h":34.0,"cells":[{"c":"A4","v":"إجمالي الملاحظات المرصودة","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"B4","v":"ملاحظات مفتوحة وجديدة","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"C4","v":"ملاحظات قيد التنفيذ والإصلاح","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"D4","v":"بانتظار إعادة المعاينة","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"E4","v":"ملاحظات معتمدة ومغلقة","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"F4","v":"نسبة الإنجاز والإغلاق","bg":"#F1F5F9","fg":"#475569","b":true,"al":"center"},{"c":"G4","v":""}]},{"r":5,"h":46.0,"cells":[{"c":"A5","v":20,"f":"=COUNTA('سجل الملاحظات التفصيلي'!B5:B24)","bg":"#F1F5F9","fg":"#3B82F6","b":true,"al":"center"},{"c":"B5","v":7,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!J5:J24, \"مفتوحة (جديدة)\")","bg":"#F1F5F9","fg":"#EF4444","b":true,"al":"center"},{"c":"C5","v":4,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!J5:J24, \"قيد المعالجة\")","bg":"#F1F5F9","fg":"#F59E0B","b":true,"al":"center"},{"c":"D5","v":3,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!J5:J24, \"بانتظار المعاينة\")","bg":"#F1F5F9","fg":"#0284C7","b":true,"al":"center"},{"c":"E5","v":6,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","bg":"#F1F5F9","fg":"#10B981","b":true,"al":"center"},{"c":"F5","v":0.3,"f":"=E5/A5","bg":"#F1F5F9","fg":"#8B5CF6","b":true,"al":"center","nf":"0.0%"},{"c":"G5","v":""}]},{"r":6,"h":34.0,"cells":[{"c":"A6","v":"كل التخصصات الهندسية","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"B6","v":"بانتظار بدء المعالجة","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"C6","v":"يعمل عليها المقاول حالياً","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"D6","v":"جاهزة لتفتيش الاستشاري","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"E6","v":"تم قبولها واستلامها رسمياً","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"F6","v":"النسبة المئوية المكتملة","bg":"#F1F5F9","fg":"#64748B","al":"center"},{"c":"G6","v":""}]},{"r":7,"h":28.0,"cells":[{"c":"A7","v":""},{"c":"B7","v":""},{"c":"C7","v":""},{"c":"D7","v":""},{"c":"E7","v":""},{"c":"F7","v":""},{"c":"G7","v":""}]},{"r":8,"h":40.0,"cells":[{"c":"A8","v":"📌 أولاً: توزيع ملاحظات الاستلام حسب التخصص الهندسي (Discipline Breakdown)","bg":"#334155","fg":"#FFFFFF","b":true,"cs":7},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":9,"h":40.0,"cells":[{"c":"A9","v":"التخصص الهندسي","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B9","v":"إجمالي الملاحظات","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C9","v":"المغلقة (المستلمة)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D9","v":"المعلقة (المتبقية)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E9","v":"نسبة المعالجة %","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"F9","v":"المقاول المسؤول الرئيسي","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"G9","v":"تقييم جاهزية التسليم","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":10,"h":52.0,"cells":[{"c":"A10","v":"تشطيبات معمارية (Architectural)","fg":"#1E293B","b":true},{"c":"B10","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*تشطيبات معمارية*\")","b":true,"al":"center"},{"c":"C10","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*تشطيبات معمارية*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","fg":"#166534","b":true,"al":"center"},{"c":"D10","v":0,"f":"=B10-C10","fg":"#991B1B","b":true,"al":"center"},{"c":"E10","v":1,"f":"=IF(B10>0, C10/B10, 1.0)","b":true,"al":"center","nf":"0.0%"},{"c":"F10","v":"شركة إعمار للتشطيبات المتقدمة","fg":"#475569"},{"c":"G10","v":"جاهز للتسليم 🟢","f":"=IF(D10=0, \"جاهز للتسليم 🟢\", IF(E10>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","b":true,"al":"center"}]},{"r":11,"h":52.0,"cells":[{"c":"A11","v":"أعمال خرسانية وإنشائية (Civil/Structural)","bg":"#F8FAFC","fg":"#1E293B","b":true},{"c":"B11","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال خرسانية*\")","bg":"#F8FAFC","b":true,"al":"center"},{"c":"C11","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال خرسانية*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"D11","v":0,"f":"=B11-C11","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"E11","v":1,"f":"=IF(B11>0, C11/B11, 1.0)","bg":"#F8FAFC","b":true,"al":"center","nf":"0.0%"},{"c":"F11","v":"شركة الصروح للمقاولات العامة","bg":"#F8FAFC","fg":"#475569"},{"c":"G11","v":"جاهز للتسليم 🟢","f":"=IF(D11=0, \"جاهز للتسليم 🟢\", IF(E11>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","bg":"#F8FAFC","b":true,"al":"center"}]},{"r":12,"h":52.0,"cells":[{"c":"A12","v":"أعمال كهربائية وأنظمة تيار خفيف (Electrical)","fg":"#1E293B","b":true},{"c":"B12","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال كهربائية*\")","b":true,"al":"center"},{"c":"C12","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال كهربائية*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","fg":"#166534","b":true,"al":"center"},{"c":"D12","v":0,"f":"=B12-C12","fg":"#991B1B","b":true,"al":"center"},{"c":"E12","v":1,"f":"=IF(B12>0, C12/B12, 1.0)","b":true,"al":"center","nf":"0.0%"},{"c":"F12","v":"مؤسسة الدوائر الذهبية للكهروميكانيك","fg":"#475569"},{"c":"G12","v":"جاهز للتسليم 🟢","f":"=IF(D12=0, \"جاهز للتسليم 🟢\", IF(E12>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","b":true,"al":"center"}]},{"r":13,"h":72.0,"cells":[{"c":"A13","v":"أعمال ميكانيكية وصحي وتكييف (Mechanical/Plumbing)","bg":"#F8FAFC","fg":"#1E293B","b":true},{"c":"B13","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال ميكانيكية*\")","bg":"#F8FAFC","b":true,"al":"center"},{"c":"C13","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*أعمال ميكانيكية*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"D13","v":0,"f":"=B13-C13","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"E13","v":1,"f":"=IF(B13>0, C13/B13, 1.0)","bg":"#F8FAFC","b":true,"al":"center","nf":"0.0%"},{"c":"F13","v":"مؤسسة التدفق الحديث للتكييف والصحي","bg":"#F8FAFC","fg":"#475569"},{"c":"G13","v":"جاهز للتسليم 🟢","f":"=IF(D13=0, \"جاهز للتسليم 🟢\", IF(E13>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","bg":"#F8FAFC","b":true,"al":"center"}]},{"r":14,"h":72.0,"cells":[{"c":"A14","v":"أعمال السلامة والوقاية من الحريق (Fire Fighting)","fg":"#1E293B","b":true},{"c":"B14","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*سلامة ومكافحة حريق*\")","b":true,"al":"center"},{"c":"C14","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*سلامة ومكافحة حريق*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","fg":"#166534","b":true,"al":"center"},{"c":"D14","v":0,"f":"=B14-C14","fg":"#991B1B","b":true,"al":"center"},{"c":"E14","v":1,"f":"=IF(B14>0, C14/B14, 1.0)","b":true,"al":"center","nf":"0.0%"},{"c":"F14","v":"شركة درع السلامة لأنظمة الحريق","fg":"#475569"},{"c":"G14","v":"جاهز للتسليم 🟢","f":"=IF(D14=0, \"جاهز للتسليم 🟢\", IF(E14>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","b":true,"al":"center"}]},{"r":15,"h":52.0,"cells":[{"c":"A15","v":"أعمال الموقع العام واللاندسكيب (Site Works)","bg":"#F8FAFC","fg":"#1E293B","b":true},{"c":"B15","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!D5:D24, \"*موقع عام ولاندسكيب*\")","bg":"#F8FAFC","b":true,"al":"center"},{"c":"C15","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!D5:D24, \"*موقع عام ولاندسكيب*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"D15","v":0,"f":"=B15-C15","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"E15","v":1,"f":"=IF(B15>0, C15/B15, 1.0)","bg":"#F8FAFC","b":true,"al":"center","nf":"0.0%"},{"c":"F15","v":"شركة الآفاق لتطوير المواقع","bg":"#F8FAFC","fg":"#475569"},{"c":"G15","v":"جاهز للتسليم 🟢","f":"=IF(D15=0, \"جاهز للتسليم 🟢\", IF(E15>=0.7, \"تقدم جيد 🟡\", \"يحتاج تكثيف 🔴\"))","bg":"#F8FAFC","b":true,"al":"center"}]},{"r":16,"h":52.0,"cells":[{"c":"A16","v":"الإجمالي العام لكافة التخصصات","bg":"#E2E8F0","fg":"#1E293B","b":true,"al":"center"},{"c":"B16","v":0,"f":"=SUM(B10:B15)","bg":"#E2E8F0","fg":"#1E293B","b":true,"al":"center"},{"c":"C16","v":0,"f":"=SUM(C10:C15)","bg":"#E2E8F0","fg":"#1E293B","b":true,"al":"center"},{"c":"D16","v":0,"f":"=SUM(D10:D15)","bg":"#E2E8F0","fg":"#1E293B","b":true,"al":"center"},{"c":"E16","v":0,"f":"=C16/B16","bg":"#E2E8F0","fg":"#1E293B","b":true,"al":"center","nf":"0.0%"},{"c":"F16","v":"متابعة أسبوعية مستمرة","bg":"#E2E8F0","fg":"#64748B","b":true,"al":"center"},{"c":"G16","v":"تقرير نهائي شامل","bg":"#E2E8F0","fg":"#64748B","b":true,"al":"center"}]},{"r":17,"h":28.0,"cells":[{"c":"A17","v":""},{"c":"B17","v":""},{"c":"C17","v":""},{"c":"D17","v":""},{"c":"E17","v":""},{"c":"F17","v":""},{"c":"G17","v":""}]},{"r":18,"h":40.0,"cells":[{"c":"A18","v":"⚡ ثانياً: تصنيف الملاحظات حسب درجة الخطورة والأولوية (Defect Severity Matrix)","bg":"#334155","fg":"#FFFFFF","b":true,"cs":7},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":19,"h":40.0,"cells":[{"c":"A19","v":"درجة الخطورة والأولوية","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B19","v":"الوصف الفني والاشتراط","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C19","v":"إجمالي الملاحظات","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D19","v":"تم الإغلاق","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E19","v":"المتبقي للمعالجة","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"F19","v":"المهلة الزمنية الملزمة","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"G19","v":"الأثر على شهادة الإنجاز","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":20,"h":72.0,"cells":[{"c":"A20","v":"حرج (Critical - أولوية قصوى)","fg":"#991B1B","b":true},{"c":"B20","v":"ملاحظات تعيق السلامة أو التشغيل أو التراخيص الحكومية","fg":"#475569"},{"c":"C20","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!G5:G24, \"*حرج (أولوية قصوى)*\")","b":true,"al":"center"},{"c":"D20","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!G5:G24, \"*حرج (أولوية قصوى)*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","fg":"#166534","b":true,"al":"center"},{"c":"E20","v":0,"f":"=C20-D20","fg":"#991B1B","b":true,"al":"center"},{"c":"F20","v":"24 - 48 ساعة","b":true,"al":"center"},{"c":"G20","v":"يوقف إصدار شهادة الإنجاز النهائي ⛔","b":true,"al":"center"}]},{"r":21,"h":72.0,"cells":[{"c":"A21","v":"متوسط (Major - أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true},{"c":"B21","v":"ملاحظات فنية مؤثرة في الجودة لا توقف التشغيل الأساسي","bg":"#F8FAFC","fg":"#475569"},{"c":"C21","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!G5:G24, \"*متوسط (أولوية ثانية)*\")","bg":"#F8FAFC","b":true,"al":"center"},{"c":"D21","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!G5:G24, \"*متوسط (أولوية ثانية)*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"E21","v":0,"f":"=C21-D21","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"F21","v":"3 - 5 أيام عمل","bg":"#F8FAFC","b":true,"al":"center"},{"c":"G21","v":"يسمح بالتسليم الابتدائي مع حجز ضمان ⚠️","bg":"#F8FAFC","b":true,"al":"center"}]},{"r":22,"h":52.0,"cells":[{"c":"A22","v":"بسيط (Minor - تجميلي/روتيني)","fg":"#166534","b":true},{"c":"B22","v":"ملاحظات دهانات أو نظافة أو خدوش تجميلية طفيفة","fg":"#475569"},{"c":"C22","v":0,"f":"=COUNTIF('سجل الملاحظات التفصيلي'!G5:G24, \"*بسيط (تجميلي)*\")","b":true,"al":"center"},{"c":"D22","v":0,"f":"=COUNTIFS('سجل الملاحظات التفصيلي'!G5:G24, \"*بسيط (تجميلي)*\", 'سجل الملاحظات التفصيلي'!J5:J24, \"معتمدة ومغلقة\")","fg":"#166534","b":true,"al":"center"},{"c":"E22","v":0,"f":"=C22-D22","fg":"#991B1B","b":true,"al":"center"},{"c":"F22","v":"7 - 10 أيام عمل","b":true,"al":"center"},{"c":"G22","v":"تُعالج خلال فترة الصيانة والضمان 🟢","b":true,"al":"center"}]}]},{"name":"سجل الملاحظات التفصيلي","maxRow":26,"maxCol":12,"colWidths":[8.0,18.0,24.0,26.0,62.0,28.0,24.0,18.0,18.0,22.0,20.0,26.0],"rows":[{"r":1,"h":54.0,"cells":[{"c":"A1","v":"📝 سجل حصر وتفتيش ملاحظات الموقع والتسليم الهندسي (Master Punch List Log)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","cs":12},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":2,"h":54.0,"cells":[{"c":"A2","v":"يتم تحديث هذا السجل يومياً أثناء جولات التفتيش المشتركة بين مهندس الاستشاري المشرف ومدير الجودة وممثلي مقاولي الباطن.","fg":"#64748B","al":"center","cs":12},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":3,"h":28.0,"cells":[{"c":"A3","v":""},{"c":"B3","v":""},{"c":"C3","v":""},{"c":"D3","v":""},{"c":"E3","v":""},{"c":"F3","v":""},{"c":"G3","v":""},{"c":"H3","v":""},{"c":"I3","v":""},{"c":"J3","v":""},{"c":"K3","v":""},{"c":"L3","v":""}]},{"r":4,"h":42.0,"cells":[{"c":"A4","v":"م","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B4","v":"كود الملاحظة (ID)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C4","v":"الموقع / الدور / الزون","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D4","v":"التخصص الهندسي (Discipline)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E4","v":"الوصف الفني للملاحظة وموقع الخلل الدقيق (Defect Details)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"F4","v":"المقاول المسؤول (Subcontractor)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"G4","v":"الأولوية (Priority)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"H4","v":"تاريخ الرصد","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"I4","v":"تاريخ الحل المستهدف","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"J4","v":"الحالة التشغيلية (Status)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"K4","v":"تاريخ الاعتماد والإغلاق","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"},{"c":"L4","v":"المهندس الفاحص (Inspector)","bg":"#475569","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":5,"h":52.0,"cells":[{"c":"A5","v":1,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B5","v":"PL-AR-001","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C5","v":"الدور الأول - شقة 102 (الصالون)","bg":"#F8FAFC"},{"c":"D5","v":"تشطيبات معمارية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E5","v":"وجود تشققات شعرية في الدهان النهائي للحائط الشمالي مع عدم استواء وزنة زاوية الجبس بورد.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F5","v":"شركة إعمار للتشطيبات المتقدمة","bg":"#F8FAFC","fg":"#475569"},{"c":"G5","v":"حرج (أولوية قصوى)","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"H5","v":"2026-10-01","bg":"#F8FAFC","al":"center"},{"c":"I5","v":"2026-10-03","bg":"#F8FAFC","al":"center"},{"c":"J5","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K5","v":"2026-10-03","bg":"#F8FAFC","al":"center"},{"c":"L5","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":6,"h":52.0,"cells":[{"c":"A6","v":2,"b":true,"al":"center"},{"c":"B6","v":"PL-AR-002","fg":"#1E293B","b":true,"al":"center"},{"c":"C6","v":"الدور الأرضي - المدخل الرئيسي"},{"c":"D6","v":"تشطيبات معمارية","b":true,"al":"center"},{"c":"E6","v":"هبوط وتطبيش في بلاطات الرخام بجوار الباب الزجاجي الأوتوماتيكي وحاجة لفك وإعادة تركيب 4 بلاطات.","fg":"#1E293B"},{"c":"F6","v":"شركة إعمار للتشطيبات المتقدمة","fg":"#475569"},{"c":"G6","v":"حرج (أولوية قصوى)","fg":"#991B1B","b":true,"al":"center"},{"c":"H6","v":"2026-10-01","al":"center"},{"c":"I6","v":"2026-10-04","al":"center"},{"c":"J6","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K6","v":"2026-10-04","al":"center"},{"c":"L6","v":"م. أحمد الغامدي","fg":"#475569","al":"center"}]},{"r":7,"h":52.0,"cells":[{"c":"A7","v":3,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B7","v":"PL-EL-003","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C7","v":"القبو 1 - غرفة لوحات الكهرباء الرئيسي","bg":"#F8FAFC"},{"c":"D7","v":"أعمال كهربائية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E7","v":"عدم اكتمال ترقيم وتسمية القواطع (Ferrules & Circuit Directory) على لوحة التوزيع MDB-B1.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F7","v":"مؤسسة الدوائر الذهبية للكهروميكانيك","bg":"#F8FAFC","fg":"#475569"},{"c":"G7","v":"متوسط (أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true,"al":"center"},{"c":"H7","v":"2026-10-02","bg":"#F8FAFC","al":"center"},{"c":"I7","v":"2026-10-06","bg":"#F8FAFC","al":"center"},{"c":"J7","v":"بانتظار المعاينة","bg":"#E0F2FE","fg":"#075985","b":true,"al":"center"},{"c":"K7","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L7","v":"م. فهد السبيعي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":8,"h":52.0,"cells":[{"c":"A8","v":4,"b":true,"al":"center"},{"c":"B8","v":"PL-ME-004","fg":"#1E293B","b":true,"al":"center"},{"c":"C8","v":"الدور الثاني - ممر المكاتب الغربي"},{"c":"D8","v":"أعمال ميكانيكية","b":true,"al":"center"},{"c":"E8","v":"تسريب مياه متقطع من وصلة درين التكييف المخفي (FCU-204) أعلى السقف المستعار وتلف بلاطتين أرمسترونج.","fg":"#1E293B"},{"c":"F8","v":"مؤسسة التدفق الحديث للتكييف والصحي","fg":"#475569"},{"c":"G8","v":"حرج (أولوية قصوى)","fg":"#991B1B","b":true,"al":"center"},{"c":"H8","v":"2026-10-02","al":"center"},{"c":"I8","v":"2026-10-04","al":"center"},{"c":"J8","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K8","v":"2026-10-04","al":"center"},{"c":"L8","v":"م. عبد الله الشهري","fg":"#475569","al":"center"}]},{"r":9,"h":52.0,"cells":[{"c":"A9","v":5,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B9","v":"PL-CV-005","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C9","v":"السطح العلوي - بيت الدرج","bg":"#F8FAFC"},{"c":"D9","v":"أعمال خرسانية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E9","v":"وجود تعشيش سطحي وتمليح في جسر السطح الخرساني الخارجي وبحاجة لمعالجة بمونة إيبوكسية غير قابلة للانكماش.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F9","v":"شركة الصروح للمقاولات العامة","bg":"#F8FAFC","fg":"#475569"},{"c":"G9","v":"متوسط (أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true,"al":"center"},{"c":"H9","v":"2026-10-02","bg":"#F8FAFC","al":"center"},{"c":"I9","v":"2026-10-07","bg":"#F8FAFC","al":"center"},{"c":"J9","v":"قيد المعالجة","bg":"#FEF9C3","fg":"#854D0E","b":true,"al":"center"},{"c":"K9","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L9","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":10,"h":52.0,"cells":[{"c":"A10","v":6,"b":true,"al":"center"},{"c":"B10","v":"PL-FF-006","fg":"#1E293B","b":true,"al":"center"},{"c":"C10","v":"الدور الثالث - مخرج الطوارئ رقم 2"},{"c":"D10","v":"سلامة ومكافحة حريق","b":true,"al":"center"},{"c":"E10","v":"عدم إحكام غلق باب الطوارئ المقاوم للحريق تلقائياً بسبب عطل بذراع الغلق الهيدروليكي (Door Closer).","fg":"#1E293B"},{"c":"F10","v":"شركة درع السلامة لأنظمة الحريق","fg":"#475569"},{"c":"G10","v":"حرج (أولوية قصوى)","fg":"#991B1B","b":true,"al":"center"},{"c":"H10","v":"2026-10-03","al":"center"},{"c":"I10","v":"2026-10-04","al":"center"},{"c":"J10","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K10","v":"2026-10-04","al":"center"},{"c":"L10","v":"م. سامي الحربي","fg":"#475569","al":"center"}]},{"r":11,"h":52.0,"cells":[{"c":"A11","v":7,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B11","v":"PL-AR-007","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C11","v":"الدور الأرضي - دورات مياه الضيوف","bg":"#F8FAFC"},{"c":"D11","v":"تشطيبات معمارية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E11","v":"عدم تناسق لون روبة الترويبة (Grout) لبلاط السيراميك وظهور فراغات حول صفايات الصرف.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F11","v":"شركة إعمار للتشطيبات المتقدمة","bg":"#F8FAFC","fg":"#475569"},{"c":"G11","v":"بسيط (تجميلي)","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"H11","v":"2026-10-03","bg":"#F8FAFC","al":"center"},{"c":"I11","v":"2026-10-09","bg":"#F8FAFC","al":"center"},{"c":"J11","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K11","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L11","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":12,"h":52.0,"cells":[{"c":"A12","v":8,"b":true,"al":"center"},{"c":"B12","v":"PL-EL-008","fg":"#1E293B","b":true,"al":"center"},{"c":"C12","v":"الدور الثاني - قاعة الاجتماعات الكبرى"},{"c":"D12","v":"أعمال كهربائية","b":true,"al":"center"},{"c":"E12","v":"عطل في 2 كشاف إضاءة سبوت لايت ليد وعدم استجابة مفتاح التعتيم الديمر (Dimmer Switch).","fg":"#1E293B"},{"c":"F12","v":"مؤسسة الدوائر الذهبية للكهروميكانيك","fg":"#475569"},{"c":"G12","v":"بسيط (تجميلي)","fg":"#166534","b":true,"al":"center"},{"c":"H12","v":"2026-10-04","al":"center"},{"c":"I12","v":"2026-10-08","al":"center"},{"c":"J12","v":"قيد المعالجة","bg":"#FEF9C3","fg":"#854D0E","b":true,"al":"center"},{"c":"K12","v":"-","al":"center"},{"c":"L12","v":"م. فهد السبيعي","fg":"#475569","al":"center"}]},{"r":13,"h":52.0,"cells":[{"c":"A13","v":9,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B13","v":"PL-ME-009","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C13","v":"الدور الأول - المطبخ المركزي","bg":"#F8FAFC"},{"c":"D13","v":"أعمال ميكانيكية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E13","v":"اهتزاز ملحوظ وضوضاء أعلى من الحدود المسموح بها في مروحة شفط الهواء الصندوقية (Inline Fan).","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F13","v":"مؤسسة التدفق الحديث للتكييف والصحي","bg":"#F8FAFC","fg":"#475569"},{"c":"G13","v":"متوسط (أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true,"al":"center"},{"c":"H13","v":"2026-10-04","bg":"#F8FAFC","al":"center"},{"c":"I13","v":"2026-10-08","bg":"#F8FAFC","al":"center"},{"c":"J13","v":"بانتظار المعاينة","bg":"#E0F2FE","fg":"#075985","b":true,"al":"center"},{"c":"K13","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L13","v":"م. عبد الله الشهري","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":14,"h":52.0,"cells":[{"c":"A14","v":10,"b":true,"al":"center"},{"c":"B14","v":"PL-SW-010","fg":"#1E293B","b":true,"al":"center"},{"c":"C14","v":"الفناء الخارجي - مواقف السيارات الشمالية"},{"c":"D14","v":"موقع عام ولاندسكيب","b":true,"al":"center"},{"c":"E14","v":"تجمع مياه راكدة بميول الإسفلت بجوار الرصيف رقم 4 وبحاجة لتعديل الميول نحو بالوعة صرف المطر.","fg":"#1E293B"},{"c":"F14","v":"شركة الآفاق لتطوير المواقع","fg":"#475569"},{"c":"G14","v":"متوسط (أولوية ثانية)","fg":"#854D0E","b":true,"al":"center"},{"c":"H14","v":"2026-10-05","al":"center"},{"c":"I14","v":"2026-10-10","al":"center"},{"c":"J14","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K14","v":"-","al":"center"},{"c":"L14","v":"م. أحمد الغامدي","fg":"#475569","al":"center"}]},{"r":15,"h":52.0,"cells":[{"c":"A15","v":11,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B15","v":"PL-AR-011","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C15","v":"الدور الرابع - الشقة رقم 401","bg":"#F8FAFC"},{"c":"D15","v":"تشطيبات معمارية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E15","v":"خدوش سطحية على درفة باب الخشب القشرة الطبيعية وتآكل في شريط السكلو الألمنيوم السفلي.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F15","v":"شركة إعمار للتشطيبات المتقدمة","bg":"#F8FAFC","fg":"#475569"},{"c":"G15","v":"بسيط (تجميلي)","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"H15","v":"2026-10-05","bg":"#F8FAFC","al":"center"},{"c":"I15","v":"2026-10-11","bg":"#F8FAFC","al":"center"},{"c":"J15","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K15","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L15","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":16,"h":52.0,"cells":[{"c":"A16","v":12,"b":true,"al":"center"},{"c":"B16","v":"PL-EL-012","fg":"#1E293B","b":true,"al":"center"},{"c":"C16","v":"القبو 2 - مخرج سيارات الزوار"},{"c":"D16","v":"أعمال كهربائية","b":true,"al":"center"},{"c":"E16","v":"عدم عمل كشافات الإضاءة التوضيحية للطوارئ (Emergency Exit Lights) عند فصل التيار التجريبي.","fg":"#1E293B"},{"c":"F16","v":"مؤسسة الدوائر الذهبية للكهروميكانيك","fg":"#475569"},{"c":"G16","v":"حرج (أولوية قصوى)","fg":"#991B1B","b":true,"al":"center"},{"c":"H16","v":"2026-10-05","al":"center"},{"c":"I16","v":"2026-10-07","al":"center"},{"c":"J16","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K16","v":"2026-10-07","al":"center"},{"c":"L16","v":"م. فهد السبيعي","fg":"#475569","al":"center"}]},{"r":17,"h":52.0,"cells":[{"c":"A17","v":13,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B17","v":"PL-CV-013","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C17","v":"القبو 1 - حائط القص الشرقي","bg":"#F8FAFC"},{"c":"D17","v":"أعمال خرسانية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E17","v":"رطوبة وتزهر أملاح في الزاوية السفلية لجدار القص وبحاجة لكشف عزل البدروم الخارجي وحقن فواصل الصب.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F17","v":"شركة الصروح للمقاولات العامة","bg":"#F8FAFC","fg":"#475569"},{"c":"G17","v":"حرج (أولوية قصوى)","bg":"#F8FAFC","fg":"#991B1B","b":true,"al":"center"},{"c":"H17","v":"2026-10-06","bg":"#F8FAFC","al":"center"},{"c":"I17","v":"2026-10-10","bg":"#F8FAFC","al":"center"},{"c":"J17","v":"قيد المعالجة","bg":"#FEF9C3","fg":"#854D0E","b":true,"al":"center"},{"c":"K17","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L17","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":18,"h":52.0,"cells":[{"c":"A18","v":14,"b":true,"al":"center"},{"c":"B18","v":"PL-AR-014","fg":"#1E293B","b":true,"al":"center"},{"c":"C18","v":"الدور الثالث - شقة 303 (البلكونة)"},{"c":"D18","v":"تشطيبات معمارية","b":true,"al":"center"},{"c":"E18","v":"ميول بلاط أرضية البلكونة معاكس نحو داخل الغرفة بدلاً من الصفاية وتجمع خفيف للمياه.","fg":"#1E293B"},{"c":"F18","v":"شركة إعمار للتشطيبات المتقدمة","fg":"#475569"},{"c":"G18","v":"حرج (أولوية قصوى)","fg":"#991B1B","b":true,"al":"center"},{"c":"H18","v":"2026-10-06","al":"center"},{"c":"I18","v":"2026-10-09","al":"center"},{"c":"J18","v":"بانتظار المعاينة","bg":"#E0F2FE","fg":"#075985","b":true,"al":"center"},{"c":"K18","v":"-","al":"center"},{"c":"L18","v":"م. أحمد الغامدي","fg":"#475569","al":"center"}]},{"r":19,"h":52.0,"cells":[{"c":"A19","v":15,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B19","v":"PL-ME-015","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C19","v":"غرفة المضخات المركزية - القبو 2","bg":"#F8FAFC"},{"c":"D19","v":"أعمال ميكانيكية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E19","v":"مقياس ضغط المياه (Pressure Gauge) على خط الطرد مكسور المؤشر وبحاجة للاستبدال والمعايرة.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F19","v":"مؤسسة التدفق الحديث للتكييف والصحي","bg":"#F8FAFC","fg":"#475569"},{"c":"G19","v":"بسيط (تجميلي)","bg":"#F8FAFC","fg":"#166534","b":true,"al":"center"},{"c":"H19","v":"2026-10-07","bg":"#F8FAFC","al":"center"},{"c":"I19","v":"2026-10-12","bg":"#F8FAFC","al":"center"},{"c":"J19","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K19","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L19","v":"م. عبد الله الشهري","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":20,"h":52.0,"cells":[{"c":"A20","v":16,"b":true,"al":"center"},{"c":"B20","v":"PL-FF-016","fg":"#1E293B","b":true,"al":"center"},{"c":"C20","v":"الدور الثاني - ممر المصاعد"},{"c":"D20","v":"سلامة ومكافحة حريق","b":true,"al":"center"},{"c":"E20","v":"صندوق حريق جداري (FHC) ينقصه مفتاح الزجاج المطرقة وفوهة خرطوم المياه غير مثبتة بإحكام.","fg":"#1E293B"},{"c":"F20","v":"شركة درع السلامة لأنظمة الحريق","fg":"#475569"},{"c":"G20","v":"متوسط (أولوية ثانية)","fg":"#854D0E","b":true,"al":"center"},{"c":"H20","v":"2026-10-07","al":"center"},{"c":"I20","v":"2026-10-10","al":"center"},{"c":"J20","v":"معتمدة ومغلقة","bg":"#DCFCE7","fg":"#166534","b":true,"al":"center"},{"c":"K20","v":"2026-10-09","al":"center"},{"c":"L20","v":"م. سامي الحربي","fg":"#475569","al":"center"}]},{"r":21,"h":52.0,"cells":[{"c":"A21","v":17,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B21","v":"PL-AR-017","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C21","v":"الدور الأرضي - بهو الاستقبال","bg":"#F8FAFC"},{"c":"D21","v":"تشطيبات معمارية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E21","v":"فراغات في السيليكون الإنشائي الفاصل بين الواجهة الزجاجية الكيرتن وول وحجر الواجهات الخارجي.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F21","v":"شركة إعمار للتشطيبات المتقدمة","bg":"#F8FAFC","fg":"#475569"},{"c":"G21","v":"متوسط (أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true,"al":"center"},{"c":"H21","v":"2026-10-08","bg":"#F8FAFC","al":"center"},{"c":"I21","v":"2026-10-12","bg":"#F8FAFC","al":"center"},{"c":"J21","v":"قيد المعالجة","bg":"#FEF9C3","fg":"#854D0E","b":true,"al":"center"},{"c":"K21","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L21","v":"م. أحمد الغامدي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":22,"h":52.0,"cells":[{"c":"A22","v":18,"b":true,"al":"center"},{"c":"B22","v":"PL-SW-018","fg":"#1E293B","b":true,"al":"center"},{"c":"C22","v":"المدخل الجنوبي - منحدر ذوي الإعاقة"},{"c":"D22","v":"موقع عام ولاندسكيب","b":true,"al":"center"},{"c":"E22","v":"دهان الخطوط التحذيرية الصفراء ومانع الانزلاق (Anti-slip) غير مكتمل الطبقات وبحاجة لوجه إضافي.","fg":"#1E293B"},{"c":"F22","v":"شركة الآفاق لتطوير المواقع","fg":"#475569"},{"c":"G22","v":"بسيط (تجميلي)","fg":"#166534","b":true,"al":"center"},{"c":"H22","v":"2026-10-08","al":"center"},{"c":"I22","v":"2026-10-13","al":"center"},{"c":"J22","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K22","v":"-","al":"center"},{"c":"L22","v":"م. أحمد الغامدي","fg":"#475569","al":"center"}]},{"r":23,"h":52.0,"cells":[{"c":"A23","v":19,"bg":"#F8FAFC","b":true,"al":"center"},{"c":"B23","v":"PL-EL-019","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"C23","v":"الدور الرابع - غرفة الخوادم IT","bg":"#F8FAFC"},{"c":"D23","v":"أعمال كهربائية","bg":"#F8FAFC","b":true,"al":"center"},{"c":"E23","v":"كيابل الشبكة والداتا غير مرتبة داخل الكبائن وتفتقر لبطاقات الترقيم القياسية (Cable Labeling).","bg":"#F8FAFC","fg":"#1E293B"},{"c":"F23","v":"مؤسسة الدوائر الذهبية للكهروميكانيك","bg":"#F8FAFC","fg":"#475569"},{"c":"G23","v":"متوسط (أولوية ثانية)","bg":"#F8FAFC","fg":"#854D0E","b":true,"al":"center"},{"c":"H23","v":"2026-10-09","bg":"#F8FAFC","al":"center"},{"c":"I23","v":"2026-10-13","bg":"#F8FAFC","al":"center"},{"c":"J23","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K23","v":"-","bg":"#F8FAFC","al":"center"},{"c":"L23","v":"م. فهد السبيعي","bg":"#F8FAFC","fg":"#475569","al":"center"}]},{"r":24,"h":52.0,"cells":[{"c":"A24","v":20,"b":true,"al":"center"},{"c":"B24","v":"PL-AR-020","fg":"#1E293B","b":true,"al":"center"},{"c":"C24","v":"الدور الأول - الممر الجنوبي"},{"c":"D24","v":"تشطيبات معمارية","b":true,"al":"center"},{"c":"E24","v":"آثار بصمات وأتربة غبار على دهان الجدران وبحاجة لتنظيف شامل وتسليم نهائي خالي من العيوب.","fg":"#1E293B"},{"c":"F24","v":"شركة إعمار للتشطيبات المتقدمة","fg":"#475569"},{"c":"G24","v":"بسيط (تجميلي)","fg":"#166534","b":true,"al":"center"},{"c":"H24","v":"2026-10-09","al":"center"},{"c":"I24","v":"2026-10-14","al":"center"},{"c":"J24","v":"مفتوحة (جديدة)","bg":"#FEE2E2","fg":"#991B1B","b":true,"al":"center"},{"c":"K24","v":"-","al":"center"},{"c":"L24","v":"م. أحمد الغامدي","fg":"#475569","al":"center"}]},{"r":25,"h":28.0,"cells":[{"c":"A25","v":""},{"c":"B25","v":""},{"c":"C25","v":""},{"c":"D25","v":""},{"c":"E25","v":""},{"c":"F25","v":""},{"c":"G25","v":""},{"c":"H25","v":""},{"c":"I25","v":""},{"c":"J25","v":""},{"c":"K25","v":""},{"c":"L25","v":""}]},{"r":26,"h":72.0,"cells":[{"c":"A26","v":"مدير ضبط الجودة بالمشروع (QA/QC):\nالمهندس / ........................\nالتوقيع: .................. التاريخ: .../ .../ 2026","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true},{"c":"D26","v":""},{"c":"E26","v":"مدير المشروع للمقاول الرئيسي:\nالمهندس / ........................\nالتوقيع: .................. التاريخ: .../ .../ 2026","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true},{"c":"H26","v":""},{"c":"I26","v":""},{"c":"J26","v":"المهندس الاستشاري المقيم المشرف:\nالمهندس / ........................\nالتوقيع: .................. التاريخ: .../ .../ 2026","bg":"#F1F5F9","b":true,"al":"center","cs":3},{"skip":true},{"skip":true}]}]},{"name":"دليل إجراءات التسليم الهندسي","maxRow":8,"maxCol":5,"colWidths":[24.0,24.0,32.0,22.0,32.0],"rows":[{"r":1,"h":54.0,"cells":[{"c":"A1","v":"📜 الدليل الإجرائي لإدارة ملاحظات الموقع وإصدار شهادة التسليم الابتدائي (TOC)","bg":"#1E293B","fg":"#FFFFFF","b":true,"al":"center","cs":5},{"skip":true},{"skip":true},{"skip":true},{"skip":true}]},{"r":2,"h":28.0,"cells":[{"c":"A2","v":""},{"c":"B2","v":""},{"c":"C2","v":""},{"c":"D2","v":""},{"c":"E2","v":""}]},{"r":3,"h":40.0,"cells":[{"c":"A3","v":"المرحلة الإجرائية","bg":"#334155","fg":"#FFFFFF","b":true,"al":"center"},{"c":"B3","v":"المرجع التعاقدي / الكود","bg":"#334155","fg":"#FFFFFF","b":true,"al":"center"},{"c":"C3","v":"الإجراء الفني المطلوب","bg":"#334155","fg":"#FFFFFF","b":true,"al":"center"},{"c":"D3","v":"المسؤولية التنفيذية","bg":"#334155","fg":"#FFFFFF","b":true,"al":"center"},{"c":"E3","v":"الأثر القانوني والمالي","bg":"#334155","fg":"#FFFFFF","b":true,"al":"center"}]},{"r":4,"h":52.0,"cells":[{"c":"A4","v":"1. طلب الفحص المشترك (Joint Inspection)","fg":"#1E293B","b":true,"al":"center"},{"c":"B4","v":"فيديك المادة 10.1 + SBC 201","fg":"#1E293B","al":"center"},{"c":"C4","v":"يقدم المقاول إشعاراً خطياً قبل 14 يوماً من التاريخ المتوقع للاكتمال الجوهري للأعمال.","fg":"#1E293B"},{"c":"D4","v":"المقاول الرئيسي","fg":"#1E293B","al":"center"},{"c":"E4","v":"بدء تشكيل لجنة الاستلام الميدانية الرسمية.","fg":"#1E293B"}]},{"r":5,"h":72.0,"cells":[{"c":"A5","v":"2. إعداد قائمة الملاحظات (Snag List)","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"B5","v":"مواصفات إدارة الجودة ISO 9001","bg":"#F8FAFC","fg":"#1E293B","al":"center"},{"c":"C5","v":"يقوم الاستشاري بحصر كافة العيوب التشطيبية غير الجوهرية وتصنيفها حسب الأولوية.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"D5","v":"الاستشاري المشرف","bg":"#F8FAFC","fg":"#1E293B","al":"center"},{"c":"E5","v":"إلزام المقاول بجدول زمني لمعالجة الملاحظات.","bg":"#F8FAFC","fg":"#1E293B"}]},{"r":6,"h":72.0,"cells":[{"c":"A6","v":"3. إصدار شهادة التسليم الابتدائي (TOC)","fg":"#1E293B","b":true,"al":"center"},{"c":"B6","v":"عقود فيديك المادة 10.2","fg":"#1E293B","al":"center"},{"c":"C6","v":"تصدر الشهادة إذا كانت الملاحظات المتبقية طفيفة ولا تعيق الاستخدام المقصود للمشروع.","fg":"#1E293B"},{"c":"D6","v":"الاستشاري والمالك","fg":"#1E293B","al":"center"},{"c":"E6","v":"توقف احتساب غرامات التأخير وانتقال مسؤولية الحراسة للمالك.","fg":"#1E293B"}]},{"r":7,"h":72.0,"cells":[{"c":"A7","v":"4. الإفراج عن الدفعة المحتجزة جزئياً","bg":"#F8FAFC","fg":"#1E293B","b":true,"al":"center"},{"c":"B7","v":"المادة 14.9 من عقد فيديك","bg":"#F8FAFC","fg":"#1E293B","al":"center"},{"c":"C7","v":"يُصرف 50% من محجوز الضمان (Retention Money) مقابل تقديم خطاب ضمان صيانة.","bg":"#F8FAFC","fg":"#1E293B"},{"c":"D7","v":"الإدارة المالية للمشروع","bg":"#F8FAFC","fg":"#1E293B","al":"center"},{"c":"E7","v":"تحرير سيولة مالية للمقاول الرئيسي.","bg":"#F8FAFC","fg":"#1E293B"}]},{"r":8,"h":72.0,"cells":[{"c":"A8","v":"5. فترة الإشعار بالعيوب (DLP)","fg":"#1E293B","b":true,"al":"center"},{"c":"B8","v":"المادة 11 من عقد فيديك","fg":"#1E293B","al":"center"},{"c":"C8","v":"فترة تمتد عادة لمدة 365 يوماً (سنة كاملة) يلتزم فيها المقاول بإصلاح أي عيب يظهر.","fg":"#1E293B"},{"c":"D8","v":"المقاول والاستشاري","fg":"#1E293B","al":"center"},{"c":"E8","v":"المحافظة على جودة المنشأ قبل إصدار شهادة الأداء النهائية.","fg":"#1E293B"}]}]}]}